The 16,000 SF Black Hawk College project created a welcoming entrance for all students, especially new and prospective students. The goal of this project was to create a new “front door” for the Black Hawk QC Campus.
Bush Construction was able to construct precisely what the college wanted while completing the project 4 months ahead of schedule. The addition of several owner-requested change orders were executed to ensure the client’s complete satisfaction with all aspects of the project.
We were able to coordinate these changes, while never losing sight of our schedule. This early completion allowed the owner to begin operations well before the anticipated timeframe.
Demolition and construction activities commenced while the semester was in session. To accommodate the students, flooring in existing corridors needed to be completed over weekends and holidays. It is our goal, at Bush Construction, to work closely with the client to meet their needs, especially when that involves working in an occupied space.